September 23 – 27 (Phase 3)
- Grading and installing pavement base for bike trail
October 7 – 11 (Phase 3)
- Planting
- Pour foundation and entryway at Main Street and Davidson
October 14 – 18 (Phase 1-3)
- Base pave bike trail (Phase 3)
- Install street light foundations
- Perform survey for location of two parking lot islands in front of 3232 Main Street
October 21 -25 (Phase 1-3)
- Tree planting
- Install irrigation laterals for new trees
- Install decomposite granite (DG) (Phase 3)
October 28 – November 1 (Phase 1-2)
- Trench and install electrical conduit for irrigation for two parking lot islands
- Demo of asphalt for parking lot islands
- Prepare subgrade for parking lot islands
- Form island for cement pour
November 4 – 8
- Pave bike trail (Phase 3)
November 11-15
Install street lights (3) at:
Main Street & Central Ave
Main Street & Burnell Ave
Main Street & Davidson Ave
September 3-6 (Phase 1 & 2)
- Set-up traffic control for closure of Central Ave
- Demo asphalt of railroad crossing
- Prepare subgrade for asphalt, curb, gutter, and sidewalk
- Form curb and gutter at Lemon Grove Ave. and Main Street
September 9-13 (Phase 1 & 2)
- Form curb and gutter at Lemon Grove Ave. and Main Street
- Pour curb and gutter at Lemon Grove Ave. and Main Street
- Form sidewalk and pedestrian ramp at Lemon Grove Ave. and Main Street
September 16-20 (Phase 1 & 2)
- Form sidewalk and pedestrian ramp at Lemon Grove and Main Street
- Pour sidewalk at Lemon Grove Ave. and Main Street
- Pave asphalt at Lemon Grove Ave. and Main Street crossing
- Continue grading subgrade for DG and asphalt (Phase 3)
Important Notice: Road Closure
Central Ave at Lemon Grove Ave Closed Starting on September 3, 2024
Central Ave at Lemon Grove Ave will close to westbound and eastbound vehicular traffic for Phase 1-2 of the Connect Main Street Project. The affected area will remain open to pedestrians. The road closure is projected to last for approximately 4 weeks. Detour routes will be indicated.
The purpose of the road closure is to provide for pavement and striping improvements around the MTS rail crossing, a sidewalk and an ADA ramp on the southwest side of Central Ave/Lemon Grove Ave, landscaping, and minor traffic signal modifications.
We apologize for any inconvenience this may cause. If you have any questions, please call the Department of Public Works at 619-825-3810 between the hours of 7:30 a.m. – 5:30 p.m.
Click here for the Traffic Control Plan
August 5-9 (Phase 3)
- Asphalt concrete grading and preparing subgrade
- Installing asphalt pavement at Davidson and Main Street
August 12-16
- Asphalt concrete grading and preparing subgrade
- Installing asphalt of pedestrian and bikeway
- Installing irrigation mainline, laterals, valves and bio barriers
August 19-23
- Installing irrigation mainline, laterals, valves and bio barriers
- Form sidewalk and pedestrian ramp at Lemon Grove and Main Street
- Pour sidewalk at Lemon Grove Ave. and Main Street
- Pave asphalt at Lemon Grove Ave. and Main Street crossing
- Continue grading subgrade for DG and asphalt (Phase 3)
March 18 — 27
Construction crews will be grading, pouring, and forming curb and gutter between Central Ave and Burnell Ave.
March 11, 2024
- One-way traffic control will be set up in the southerly direction on Main Street from Central Ave to Burnell Ave. Main Street northbound is closed from Burnell Ave to Central Ave.
- Construction crews will mill asphalt to prepare the subgrade for public improvements
- Construction crews will trench for utility installation